DOW Silicones - W960 boiler - Suction duct

After doing research on the efficiency of the boiler, the conclusion was made that the potential of the boiler was far from met. To fix this, a redesign of the suction duct had to be made and the current suction duct had to be replaced.

Challenge

  • Creating an efficient intake duct to reach the boiler's potential.
  • The suction channel had to blend into the surrounding components.
  • Create a laminar flow with as little resistance as possible.

Solution

  • CFD study to obtain exact dimensions.
  • Painting the extractor in a desert/sand color.

Facts

Noise control

Customer:

DOW Silicones UK Ltd

Location:

Penarth, United Kingdom

Solutions:

Process ducting