Skip to main content

Your Emissions in control

Two stacks letting out hot air after the CHP

BPK Duffel - CHP and BoP

Commissioned by INNIO Jenbacher, we have installed four flue gas systems for 4.4MW CHP installations at BPK Duffel. BPK has been a key player in the Belgian horticultural sector for more than 50 years.  With this installation, BPK is able to generate clean and efficient energy, recover heat and remove CO2 from the gasses, all while reducing the noise to below the legal standard.

Challenge

  • Complete pollution, noise, heat and odor control system.
  • CO2 reduction.

Solution

  • Full BoP with engineering & fabrication.
  • SCR/CO2 production modules.
  • EGHE & condensing modules.
  • Silencers & exhaust chimneys.
  • Noise enclosures.
  • Soot filters.

Facts

Noise control
Heat Recovery
Pollution control
Odor control

Customer:

INNIO Jenbacher

Location:

Duffel, Belgium

Solutions:

Acoustical-enclosures, Heat-exchanger, SCR/Oxycat, Silencers, Soot filter, Stack

ARRAY

Hoogeveenenweg 93
2913 LV Nieuwerkerk aan den IJssel

Nederland

This email address is being protected from spambots. You need JavaScript enabled to view it.
+31 (0) 10 765 12 00

 

LINKS

Privacy statement

 

ARRAY

Hoogeveenenweg 93
2913 LV Nieuwerkerk aan den IJssel

Nederland

This email address is being protected from spambots. You need JavaScript enabled to view it.
+31 (0) 10 765 12 00

 

LINKS

Privacy Statement